Environmental Issues
Public registers
POEO Public Register
Licences, applications and notices search
Penalty notices search
Enforceable undertakings search
Enforceable undertakings media releases
Exemptions and approvals search
Prosecutions or civil proceedings search
Terms of use: POEO public register
Licensing FAQs
List of licences
Unlicensed premises regulated by the EPA
Contaminated land record of notices
About the record of notices
List of notified sites
Tips for searching
Disclaimer
Dangerous goods licences
Pesticide licences
Radiation licences
Home
Public registers
POEO Public Register
Licences, applications and notices search
Non-Compliance detail
Summary
Licence number:
12290
Annual Return Start:
18 Apr 2007
Annual Return End:
31 Mar 2008
Date Received:
30 May 2008
Licence Condition number
Type of non-compliance
EPA actions
No. of times occurred
L8.1
The airblast overpressure exceeded 120 dB (Lin Peak) on shot number Ocrica 7 (03/07/07) and WC131 (15/05/07). The overpressure reading was from Railwayview.
Penalty Notice issued
2
L3.3
Total Suspended Solids during wet weather discharges exceeded limit from 20-21/08/07 at SD7, SD9, SD10.
EPA has written to licensee regarding non-compliance and relevant action
1
L3.3
pH during wet weather discharge was 9.0 at EPA point 10 on 05/02/08.
EPA to monitor future compliance with this condition
1
L6.1
Noise levels exceeded limit at Railway View on 30/05/07, 30-31/08/07, 11/12/07, 08/01/08, 18/03/08; Railway View, Old Colliery, Mountain View and Escott on 11-12/07/07; Cintra on 18/09/07, 11/12/007.
EPA has written to licensee regarding non-compliance and relevant action
7
L1.1
Breach in Void water structure. Discharge of potentially contaminated water, 14-17/07/07.
Non-compliance(s) under investigation
1
M2.1
The continuous weather data recording was interrupted on 5 occasions during the period, 6-31/07/07, 4-8/08/07, 11-16/12/07, 2-4/02/08, 20-25/03/08.
Appropriate Action taken by licensee
5
M2.1
The HVAS sampling was not carried out on the 17/02/08 at all PM10 sites. The HVAS sampling was unable to be carried out on the 29/02/08 and 30/03/08 due to power failure at point 3. Filters not changed on sampling run 06/03/08 and 12/03/08.
EPA to monitor future compliance with this condition
4
M2.1
Groundwater was not sampled at MW1 during 12 month period.
EPA to monitor future compliance with this condition
3
M2.1
Samples sent to laboratory on 20/08/07 were not tested for Reactive Phosphorous.
EPA to monitor future compliance with this condition
1